Learn how a Canadian Bank was able to identify interruptions in value-added activities and improve productivity by more than 30%.
“With one click, all of the collected information was instantly compiled. The results stunned the continuous improvement team.”
– Associated Consulting Firm
Problem
IT projects always surpass estimated costs and time frames.
Objective
Discover the reasons for these variances and make the necessary corrections.
Methodology
Continuous improvement project: Kaizen.
Measures
With the help of UMT Plus software developed by Laubrass Inc., the improvement project members programmed, on twelve PDAs, the various possible causes of the many slowdowns experienced by the people working in the IT department. It was not the quality of work that was questioned, but rather all of the interruptions (telephone calls, faxes, queries from colleagues, etc.) that people in the department had to deal with. During 5 days, time measurements were registered for the approximately 140 IT personnel.
Results
With one click, all of the collected information was instantly compiled. The results stunned the continuous improvement team. On average, each person from the IT group was disturbed every three minutes. Furthermore, the process added value was 10%. Can you imagine people’s astonishment in light of these results? How can anyone concentrate on a project with so many interruptions?
Improvements
It was agreed upon that one hour in the morning and one hour in the afternoon would be set aside to discuss questions relating to the various projects. A preparation period was also required to ensure the time spent answering questions would be productive.
During the remainder of the day, interruptions were accepted or prohibited according to the project’s priority code. Furthermore, a room was designated for certain special projects where interruptions were forbidden.
Cost of Improvements
$0
Results After Improvements
Two months after the improvements were implemented, measurements were retaken. The personnel added value had increased from 10% to 30%.
The IT personnel are interrupted every 30 minutes on average compared to once every 3 minutes before the improvement project.